The wheel replacement project of Beijing Benz Automobile Co., Ltd.
Project location: Beijing Benz Automobile Co., Ltd.
Quantity: 5 sets
Equipment model: 4250-400 (3 sets) 3900-500 (2 sets)
Exhaust gas source: Exhaust gas from vehicle painting
Replacement reason: MRA1 rotor clogged
Original ADR manufacturer: Imported brand
Pre-replacement usage time: Less than 5 years
Replacement time: 2020.9 (1 set) 2022 (4 sets)
Due to the need for handling exhaust gases from vehicle painting in Beijing Benz Automobile Co., Ltd., the imported brand MRA1 rotary disk, which had been in use for less than 5 years, began to experience clogging issues, resulting in a decline in the efficiency of exhaust gas treatment. We have designed a phased replacement plan for it: in September 2020, 1 set of 4250-400 equipment will be replaced first, and the remaining 4 sets (2 sets of 4250-400 + 2 sets of 3900-500) will be upgraded by 2022. After the new equipment is put into use, the exhaust gas adsorption efficiency will increase by 40%, and the operation and maintenance costs will be reduced by 30%. The person in charge of the Mercedes equipment reported: "After the rotor replacement, the system stability has significantly improved. There are no more blockage alarms, and the expected environmental protection indicators have been achieved."
Main situation:


Figure 1 shows the photos taken during the on-site replacement/installation of the turbine in September 2020.


Figure 2 shows the photos taken during the on-site replacement/installation of the turbine in August 2022.


Figure 3 shows the photos taken during the on-site replacement/installation of the turbine in October 2022.